Terrace slab, 6 × 3 m at 12 cm depth
A garden terrace slab: 6 m long by 3 m wide, 12 cm depth, 10% waste, purchasing bags with an example yield of 0.0125 m³ per 25 kg bag.
plan_area = 6 × 3 = 18 m². Net volume = 18 × 0.12 = 2.16 m³. With 10% waste: 2.16 × 1.10 = 2.376 → 2.38 m³. bags = ceil(2.376 ÷ 0.0125) = ceil(190.1) = 191 bags.
2.16 m³ is the theoretical net volume; 2.38 m³ is the quantity including waste; 191 bags is the final purchase quantity. Reinforcement mesh, if used under a terrace slab, is a separate line item this tool does not size.
⚠ The 0.0125 m³ per bag yield is an editable example — check the actual yield printed on the selected bag's packaging or data sheet before ordering.
Vehicle-bearing garage slab, 5 × 5 m at 15 cm depth
A reinforced garage slab designed to carry vehicle loads: 5 m × 5 m, 15 cm depth, 10% waste, same example bag yield. Reinforcing mesh is planned but priced and sized separately.
plan_area = 5 × 5 = 25 m². Net volume = 25 × 0.15 = 3.75 m³. With 10% waste: 3.75 × 1.10 = 4.125 → 4.13 m³. bags = ceil(4.125 ÷ 0.0125) = 330 bags exactly.
At 4.13 m³, ready-mix truck delivery is often more practical than 330 hand-mixed bags — check your supplier's minimum order. Because this slab carries vehicle loads, reinforcing mesh sizing and cover depth should come from an engineer or the applicable local code, not from this calculator.
⚠ This calculator produces quantities only — it does not check whether 15 cm depth and the planned mesh are adequate for the expected vehicle load; that is a structural design question for an engineer.
Strip footing, 12 m long: bags versus ready-mix truck
A 12 m long, 0.5 m wide strip footing at 24 cm depth, 10% waste. The example compares purchasing bags against ordering a ready-mix truck, which typically has a minimum order quantity.
plan_area = 12 × 0.5 = 6 m². Net volume = 6 × 0.24 = 1.44 m³. With 10% waste: 1.44 × 1.10 = 1.584 → 1.58 m³. bags = ceil(1.584 ÷ 0.0125) = 127 bags (about 3.18 tonnes of bagged mix). At an example supplier minimum order of 1 m³, a 1.58 m³ ready-mix order clears the minimum easily.
127 bags mixed by hand is a lot of manual labour for a single footing; comparing the bagged-mix cost against a ready-mix truck's price per m³ plus delivery fee often changes the decision, especially once the minimum order is already exceeded.
⚠ Changing the selected currency only changes the display symbol — it does not convert prices you have entered for bags or for a ready-mix truck. Enter current local supplier prices in the currency you have selected, and confirm the actual minimum order quantity with the supplier, since it is not a fixed universal figure.