Foundation trench for a 20 m² extension, 12 m² dug area
Foundation trenches for a 20 m² single-storey extension: 12 m² of actual trench footprint, 80 cm dig depth, general soil bulk density 1700 kg/m³, 5% waste, 25% bulking for this clay-loam ground.
Bank volume = 12 × 0.80 = 9.6 m³. With 5% waste and 25% bulking: 9.6 × 1.05 × 1.25 = 12.6 m³ loose volume. Weight = 12.6 × 1700 = 21,420 kg (≈21.42 t).
9.6 m³ is the physical size of the trench being dug; 12.6 m³ is the loose, bulked volume that actually has to be loaded and hauled away — noticeably more than the hole itself, purely because dug soil takes up more room than undisturbed ground. Skip or truck numbers should be sized against the 12.6 m³ / 21.42 t figure, not the 9.6 m³ bank volume.
⚠ Before digging this trench, buried services along its route must be located and marked by the relevant utility service — this is a safety requirement independent of the volume calculation and is not something the calculator verifies.
Garden pond excavation, 6 m² at 100 cm depth
A garden pond dug into loamy soil: 6 m² zone, 100 cm depth, bulk density 1700 kg/m³, 5% waste, 25% bulking, skip capacity 1000 kg each, hauler's minimum truck load of 5 t.
Bank volume = 6 × 1.00 = 6.0 m³. With 5% waste and 25% bulking: 6.0 × 1.05 × 1.25 = 7.875 m³ loose volume. Weight = 7.875 × 1700 = 13,387.5 kg (≈13.39 t). Skips (1000 kg): ceil(13,387.5 ÷ 1000) = 14 skip loads. Truck: needed 13.39 t is below the 5 t minimum per load only if a single load is booked below capacity — here it exceeds the 5 t minimum, so truck_t = ceil(13,387.5 ÷ 100) ÷ 10 = 13.4 t across multiple truck loads.
A modest 6 m² pond footprint still produces over 13 tonnes of spoil to remove once bulking is applied — this is why even small excavation projects often need multiple skip collections or several truck visits, not a single load. Comparing 14 skips against multiple truck loads lets you weigh site access and cost before committing.
⚠ 25% bulking is an editable planning assumption for loamy soil, not a guaranteed figure — sandy soil typically swells less and dense clay can swell considerably more, so confirm the expected swell factor for the actual ground conditions before booking disposal capacity.
Patio sub-base excavation and disposal cost, 30 m²
Excavating a 30 m² patio area down to sub-base level: 25 cm dig depth, bulk density 1700 kg/m³, 5% waste, 25% bulking. Skip hire costs 220 per 1000 kg skip; truck haulage costs 45 per tonne plus a 60 call-out fee, with a 5 t hauler minimum.
Bank volume = 30 × 0.25 = 7.5 m³. With 5% waste and 25% bulking: 7.5 × 1.05 × 1.25 = 9.84 m³ loose volume. Weight = 9.84 × 1700 = 16,734 kg (≈16.73 t). Skips: ceil(16,734 ÷ 1000) = 17 skips → 17 × 220 = 3740. Truck: ceil(16,734 ÷ 100) ÷ 10 = 16.8 t → 16.8 × 45 + 60 = 816.
Removing this sub-base spoil in 1000 kg skips would cost roughly 3740, while a bulk truck haulage booking at 16.8 t comes to about 816 including the call-out fee — truck haulage is clearly cheaper once the load comfortably clears the 5 t minimum, provided the site has room for a truck to access and load directly. The calculator surfaces both totals so the choice is based on cost and access together, not habit.
⚠ Changing the selected currency only changes the displayed symbol — it does not convert 220, 45 or 60 into a different currency's equivalent value. Enter current local hauler or skip-hire prices in the currency you have selected, and separately confirm any tipping or landfill tax that applies to the spoil type being disposed of.